Project description: Sandbar Park improvements, Lake Road drainage, shore flood wall, shore flood wall mo. co., and building.
Bonding information:
Bond Resolution amount ($):
Sandbar Park improvements 5,500,000
Lake Road drainage 2,500,000
Shore flood wall 1,000,000
Shore flood wall mo. co. 500,000
Building 0
__________________________________________
$9,500,000
Bond Resolution date: 11/4/2021 | Meeting Results | Meeting Video
Financing as a percentage of approved bond resolution: 40.4%
Life-to-date net project cost: $3,290,479
Life-to-date net project cost as a percentage of approved bond resolution: 34.6%
Project percentage complete: 84.5%
Project Milestones and Updates:
November 7, 2024: Update on bid opening | Presentation | Video
October 23, 2024: Bid opening takes place.
September 25, 2024: Bid solicitation advertised in Webster Herald.
September 19, 2024: Resolution to solicit bids for the Sandbar Park Restaurant construction project and advertise in the September 25, 2024, edition of the Webster Herald approved by Webster Town Board.
June 13, 2024: Restaurant/Bar Update | Presentation | Video
May 2024: Cost estimates gathered for the restaurant.
April 2024: Design meetings with Town, Fantauzzo Family Brands, Passero Associates, and Campus.
March 2024: Town contracts with Passero Associates for Design Services and Campus Construction Management for Construction Management Services.
February 2024: Final approval for permit received from all agencies providing approval or waiving their involvement.
November 2023: Town submits an application to build a 2,400 square foot restaurant and bar.
December 8, 2022: Restaurant/Bar Update | Presentation | Meeting Video
November 10, 2022: Construction Update | Presentation | Meeting Video
June 23, 2022: EOI Update | Presentation | Meeting Video
April 8, 2022: Expression of Interest (EOI) Deadline
October 28, 2021: Public Meeting held at Thomas High School | Presentation | Meeting Video